GK Quiz, General Knowledge, Latest Current Affairs, Business Quiz, Management Quiz, Finance, Project Management, PMP Resources, IT Quiz, Bollywood Quiz, Finance, HR, OB, Supply Chain Management, Multiple Choice Questions, Bank PO Entrance Exam Questions, Civil Services Question Bank, Quant, Verbal, GMAT, SAT, TOEFL Resources Questions, Numerical Ability, Fun Quiz, KBC

Project Management Quiz for PMP/CIPM - 79

1. When the project is considered successful?
[A]When deliverables are by & large handed over to a client
[B]When all the deliverables as per checklist are delivered
[C]When project team members are dispersed
[D]When the total payment is received by the contractor


2. What are the methods of project evaluation?
[A]Project audits
[B]Quality control
[C]Post implementation reviews
[D]A & C


3. Which of the following are included as part of a scope statement?
[A]Project justification
[B]Project deliverables
[C]Project objectives
[D]All of the above


4. Project life cycles are very useful for _____ and _____ .
[A]Configuration management, termination
[B]Objective setting, information gathering
[C]Standardization, control
[D]Configuration management, weekly status updates


5. Work packages are used to:
[A]Represent units of work at a level where work is performed.
[B]Clearly distinguish one work package from all others assigned to a single functional group.
[C]Limit the work to be performed to relatively short periods of time.
[D]All of the above.


6. "Hard logic" in the preparation of a network refers to:
[A]Discretionay dependencies
[B]External depenencies
[C]Mandatory dependencies
[D]All of the above


7. The erection of foundation formwork before the placement of foundation concrete would be an example of a _____ dependency.
[A]Discretionary
[B]Mandatory
[C]External
[D]Soft logic


8. Sources for data on activity durations and resource requirements can be gathered from which of the following:
[A]Past project records (historical data)
[B]Commercial techniques (standard practices, rules of thumb)
[C]Past project team members knowledge (experience, oldtimers)
[D]All of the above


9. Which of the following can affect network durations?
[A]Skills of the resource pool
[B]Calendar dates
[C]Constraints
[D]A and B only


10. A completion of a local government study resides on your critical path. This would most likely be referred to as:
[A]Soft logic
[B]Hard logic
[C]An external dependency
[D]A mandatory dependency


11. A project may be undertaken to address
[A]A new business need
[B]Maintain a running process
[C]Re-work
[D]Manufacture a car battery


12. The quality considerations to be followed in the project are decided:
[A]During it's execution
[B]By the quality department
[C]At the beginning of the project
[D]Depending on the project's cost


13. The development of modern project management began in:
[A]1950
[B]1960
[C]1970
[D]1975


14. What do the three sides of the conventional triangle in project management represent?
[A]Customer, time and cost
[B]Quality, customer and scope
[C]Scope, time and quality
[D]Scope, time and cost


15. Using the diagram given below, the late start (LS) of activity F is at the beginning of day:

[A]9
[B]8
[C]7
[D]14