GK Quiz, General Knowledge, Latest Current Affairs, Business Quiz, Management Quiz, Finance, Project Management, PMP Resources, IT Quiz, Bollywood Quiz, Finance, HR, OB, Supply Chain Management, Multiple Choice Questions, Bank PO Entrance Exam Questions, Civil Services Question Bank, Quant, Verbal, GMAT, SAT, TOEFL Resources Questions, Numerical Ability, Fun Quiz, KBC

Project Management Quiz - 78

1. Who issues the warranty
[A]Manufacturer
[B]Customer
[C]Retailer
[D]A&C


2. When is warranty rights enforced against suppliers
[A]When warranty is not violated
[B]When warranty is violated
[C]During pre-delivery of goods and services
[D]Suppliers donot meet the commitment in delivery


3. In Contract close out ,one should:
[A]Measure the performance of a contracting organization based on specification and the technical aspects
[B]Measure how well did the contractor behaved
[C]Measure the personal relationship with the contractor
[D]Measure customer satisfaction


4. During contract closeout a product verification is done to:
[A]Ensure that the seller’s work is complete and satisfactorily meets all the requirements
[B]Verify the products design
[C]To document the seller’s work
[D]Verify the work completed for making seller payments.


5. Contract close out involves all of the following except:
[A]Relocating team members
[B]Formal acceptance of the work by the buyer
[C]Updating the contract file
[D]Product Verification


6. Who issue the purchase order
[A]Buyer
[B]Seller
[C]Project Manager
[D]None of the above


7. what is not the part of the purchase order close out
[A]Operating instructions
[B]Compliance with the delivery terms
[C]Preparing project management plan
[D]Vendor’s claim


8. Which is not part of core element of contract
[A]Payment terms
[B]company leave policy
[C]statement of work
[D]None of the above


9. When is the project close out reports prepared
[A]Planning stage
[B]Implementation life cycle
[C]End of the project
[D]Execution stage


10. Which documents are ensured to be closed in project close out
[A]Risk management log
[B]Project Change Log
[C]A and B
[D]None of the above


11. Which Resources Are Included In The Resource Close Out?
[A]Man
[B]Material
[C]Equipment
[D]All of the above


12. What Is Not True For Team Close Out
[A]The team resources are returned after the completion of project
[B]It is not a good practice to conduct close out meeting even if the project is terminated early.It is not a good practice to conduct close out meeting even if the project is terminated early.
[C]Meeting for close out or celebration to be conducted
[D]The project manager ensures that the stakeholders should be made aware of any remaining work


13. Which aspect is included during lessons learnt from projects?
[A]Positive
[B]Negative
[C]Both
[D]None of the above


14. What is necessary to accept a project?
[A]Project plan
[B]Meeting acceptance criteria
[C]Executing a plan
[D]Resource Allocation


15. When is the project acceptance done?
[A]Project had satisfied requirement with some minor errors/omissions
[B]Project had not satisfied the acceptance
[C]Project had satisfied the acceptance
[D]At the implementation stage


No comments:

Most Played Quizzes Last Week