GK Quiz, General Knowledge, Latest Current Affairs, Business Quiz, Management Quiz, Finance, Project Management, PMP Resources, IT Quiz, Bollywood Quiz, Finance, HR, OB, Supply Chain Management, Multiple Choice Questions, Bank PO Entrance Exam Questions, Civil Services Question Bank, Quant, Verbal, GMAT, SAT, TOEFL Resources Questions, Numerical Ability, Fun Quiz, KBC

Project Management Quiz - 72

1. The bottom-up estimates generally have an accuracy of:
[A]-25% to +75%
[B]-25% to +30%
[C]-5% to +10%
[D]+15% to -15%


2. What are the three most common cost estimating techniques?
[A]Top-down, parametric and bottom-up
[B]Analogous, top down and bottom-up
[C]Parametric, bottom-up and detailed
[D]Monte Carlo, bottom-up and parametric


3. Cost baseline can:
[A]Change during the project life cycle
[B]Be affected by scope change
[C]Be affected by change in time schedule
[D]All of the above


4. Cost baseline is:
[A]Another name for cost estimates
[B]Given by upper management
[C]Time phased budget of project that is used to measure project's cost performance
[D]Provided in the contract to the customers


5. Zero defects, Continuous quality improvement and TQM:
[A]Advocate a proactive way to improve quality
[B]Rely on the workers to implement better quality
[C]Means that there are zero defects
[D]All of the above


6. A company wants to introduce a defect free environment. The authority and capability to introduce this:
[A]Lies with the project manager
[B]Lies with the management
[C]Lies with the functional manager
[D]Lies equally with - the project manager, the functional manager and management


7. A critical path is shown in a:
[A]WBS
[B]Bar chart
[C]Project network diagram
[D]Resource histogram


8. The critical path in a project network is the path that:
[A]Is the longest path in a network
[B]Is decided by a project manager
[C]Allows some flexibility in scheduling a start time
[D]Should be executed when other activities on a non critical paths have been finished


9. Which of the following impacts the critical path?
[A]Executing a forward pass
[B]Reduce the free float of an activity
[C]Executing a backward pass
[D]Changing the task duration of a critical path activity


10. The series of interconnected activities, which determine the duration of the project is known as:
[A]The critical path
[B]The free float plan
[C]The critical work plan
[D]The management plan


11. Project X has a total budget of $9 million and was to be completed in 8 months. While reviewing the progress of the project at the end of 3 months, the following data was presented: BCWS or PV = $3 Million; BCWP or EV = $2.5 Million and ACWP or AC = $3 Million. What is Estimate at Completion if the efficiency of capital deployed will change to 100% from now onwards:
[A]$9 Million
[B]$8.5 Million
[C]$9.5 Million
[D]$10.8 Million


12. Project X has a total budget of $9 million and was to be completed in 8 months. While reviewing the progress of the project at the end of 3 months, the following data was presented: BCWS or PV = $3 Million; BCWP or EV = $2.5 Million and ACWP or AC = $3 Million. What is Estimate at Completion if the efficiency of capital deployed remains the same?
[A]$3.6 Million
[B]$10.8 Million
[C]$7.5 Million
[D]$12 Million


13. Continuous Improvement Process or CIP is a quality concept that states:
[A]What is satisfactory today may become unsatisfactory tomorrow
[B]Does not advocate any great leap forward
[C]Management should keep looking for ways to improve and change processes
[D]All of the above


14. Zero defects states that:
[A]There are zero errors in a process
[B]There is no tolerance for any defects within the system
[C]See how to improve processes in order to avoid all defects
[D]B and C


15. The modern trend in quality is to:
[A]Focus more on customer satisfaction and conformance to requirements
[B]Give the customer more than what he wants
[C]Give the customer less than what he wants
[D]Rely on worker to maintain quality