GK Quiz, General Knowledge, Latest Current Affairs, Business Quiz, Management Quiz, Finance, Project Management, PMP Resources, IT Quiz, Bollywood Quiz, Finance, HR, OB, Supply Chain Management, Multiple Choice Questions, Bank PO Entrance Exam Questions, Civil Services Question Bank, Quant, Verbal, GMAT, SAT, TOEFL Resources Questions, Numerical Ability, Fun Quiz, KBC

Project Management Quiz - 51

1. Using the situation stated in the Special window, which WBS element is behind schedule but under budget?
[A]Element P
[B]Element Q
[C]Element R
[D]Element S
[E]None of the above.



2. Using the situation stated in the Special window, which WBS element has a favorable cost variance of $150?
[A]Element P
[B]Element Q
[C]Element R
[D]Element S
[E]None of the above.



3. Using the situation stated in the Special window, the cost performance index (CPI) for WBS Element R is:
[A]0.875
[B]1.14
[C]0.952
[D]0.833
[E]1.2



4. Using the situation stated in the Special window, the schedule performance index (SPI) for WBS Element P is:
[A]1.1
[B]0.9
[C]0.956
[D]1.15
[E]0.869



5. Using the situation stated in the Special window, WBS Element Q is _____ budget by _____ percent.
[A]Over, 16.66
[B]Under, 16.66
[C]Over, 10.0
[D]Under, 10.0
[E]None of the above.



6. Using the situation stated in the Special window, a comparison of the cost schedule of August as compared to July shows that the magnitude ($ value) of the variance has _____ and the percentage change has _____.
[A]Become worse, become worse
[B]Become worse, improved
[C]Improved, increased
[D]Improved, become worse
[E]None of the above are correct



7. Using the situation stated in the Special window, the total price variance of direct material is:
[A]80245
[B]-4236
[C]-3479
[D]0.69
[E]83994



8. Using the situation stated in the Special window, the labor rate cost variance is:
[A]66927
[B]68329
[C]386
[D]-0.22
[E]18.36



9. Using the situation stated in the Special window, what is the total fixed costs for manufacturing the widgets?
[A]3000
[B]27000
[C]27270
[D]1335
[E]1000



10. Using the figure in the Special window, The critical path is:
[A]A-B-G
[B]C-G
[C]C-D
[D]E-F
[E]A-B-G and C-D



11. Using the figure in the Special window, By how many weeks can activity "F" slip without extending the end date of the project?
[A]0
[B]1
[C]2
[D]3
[E]4



12. Using the data shown in the Special window, Activities P, Q, and T are critical path activities. In order to shorten the time duration of the project, which activity should be "crashed" first?
[A]P
[B]Q
[C]R
[D]S
[E]T



13. Using the possible profit and loss outcomes shown in the Special window, find the expected profit (loss)
[A]-1000
[B]1000
[C]2000
[D]1200
[E]None of the above



14. Using the figure in the Special window, The Critical path is _____ weeks.
[A]21
[B]22
[C]23
[D]24
[E]25



15. Using the possible loss outcomes shown in the Special window, find the expected (loss)
[A]0
[B]-1300
[C]-2000
[D]-3000
[E]None of the above