GK Quiz, General Knowledge, Latest Current Affairs, Business Quiz, Management Quiz, Finance, Project Management, PMP Resources, IT Quiz, Bollywood Quiz, Finance, HR, OB, Supply Chain Management, Multiple Choice Questions, Bank PO Entrance Exam Questions, Civil Services Question Bank, Quant, Verbal, GMAT, SAT, TOEFL Resources Questions, Numerical Ability, Fun Quiz, KBC

Project Management Quiz - 19

1. The logical relationship that communicates a delay between the start/finish of one activity and the start/finish of another activity is referred to as:
[A]Slack
[B]Free float.
[C]Restricted float.
[D]Level float.
[E]Lag



2. Which of the following actions is an example of risk response:
[A]adjust project parameters (scope, time, quality ...)
[B]reduce the probability of potential project risk events
[C]reduce the consequences of potential project risk events
[D]wait until a problem actually happens, then deal with it in the most effective and efficient manner.
[E]A, B and C only



3. A comparison of completion status to baseline is referred to as _____.
[A]Earned value measurement.
[B]Percent complete.
[C]ACWP.
[D]BCWS
[E]None of above.



4. An example of coercive power would be:
[A]Demotion
[B]Reduction in wages
[C]Disciplinary layoff
[D]Reprimand
[E]All of the above



5. Job descriptions are examples of ______communications.
[A]upward
[B]downward
[C]horizontal
[D]diagonal
[E]None of the above



6. Monte Carlo simulation:
[A]Was originally developed by Dr. Carlo
[B]Is a European technique for assessing project risks
[C]assumes the future risk events will occur at random according to predetermined probability distributions
[D]is a technique to stimulate create risk event resolution
[E]A, B and C only



7. The Pareto Principle is a technique used to determine which quality control problems in a particular process should be corrected. Which of the following statements best represents the philosophy employed by this principle?
[A]In order to minimize financial losses from quality control problems, all problems which have a measureable cost should be corrected
[B]the majority of defects are caused by a small percentage of the identifiable problems. Improvement efforts should be reserved for these vital problems.
[C]in order to achieve zero defects, all quality control problems, including those which do not have a direct financial cost should be corrected.
[D]generally, 80% of the quality control problems are justifiable for correction via cost-benefit analysis. The remaining 20% are not financially worthy of improvement efforts.
[E]A and D



8. The WBS is:
[A]An organization oriented family tree of the project.
[B]A task oriented family tree of the project.
[C]A cost centered structure of the project.
[D]Only required on large complex projects where separately identifiable work packages are difficult to construct.
[E]None of the above.



9. Which of the following processes allow an unsuccessful bidder to seek remedy for contract award to another bidder.
[A]bid protest
[B]bid review
[C]award Protest
[D]award review
[E]any of the above processes can be used



10. A project team member submits a suggestion on how to improve the corporate procurement process. This is an example of _____ communication
[A]upward
[B]downward
[C]horizontal
[D]diagonal
[E]None of the above.



11. Financial compensation is the primary motivational tool for which of the following management theories of programs.
[A]Zero-defects program.
[B]theory X management.
[C]theory Y management.
[D]Quality control circles.
[E]A and C



12. In which of the following contract types is it easier to change the scope of the contract:
[A]firm fixed price
[B]fixed price plus incentive fee
[C]cost plus percentage of cost
[D]letter contract
[E]None of the above.



13. Planning activities such that predetermined resource availability pools are not exceeded is called:
[A]Resource leveling.
[B]Manpower leveling.
[C]Resource limited planning.
[D]Manpower planning.
[E]Manpower contingency planning.



14. The project charter:
[A]Expresses upper management commitment to the project.
[B]Provides that authority by which the project will be run.
[C]Establishes that organizational structure with the project.
[D]Specifies overall objectives and timeframe of the project.
[E]All of the above.



15. Which of the following areas are addressed in risk identification:
[A]environmental
[B]technical
[C]legal
[D]All of the above.
[E]A and B only



No comments:

Most Played Quizzes Last Week