GK Quiz, General Knowledge, Latest Current Affairs, Business Quiz, Management Quiz, Finance, Project Management, PMP Resources, IT Quiz, Bollywood Quiz, Finance, HR, OB, Supply Chain Management, Multiple Choice Questions, Bank PO Entrance Exam Questions, Civil Services Question Bank, Quant, Verbal, GMAT, SAT, TOEFL Resources Questions, Numerical Ability, Fun Quiz, KBC

PMP Certification Sample Paper(Project Management Quiz - 70)

1. For a network using PERT for determining activity durations, one of the activities in this network is having a standard deviation of 10 minutes. This activity has pessimistic time duration of 75 minutes. Calculate the optimistic time duration of this activity.
[A]65 minutes
[B]85 minutes
[C]135 minutes
[D]15 minutes



2. An activity has an Optimistic duration of 100 days, a Pessimistic duration of 158 days and a Most likely duration of 120 days. The time estimate which would be considered for this activity is:
[A]120 days
[B]123 days
[C]100 days
[D]160 days



3. 3 time estimates using PERT methodology is generally based on:
[A]Modified normal distribution
[B]Alpha distribution
[C]Triangular distribution
[D]None of the above



4. 3 time estimates should be used when the level of uncertainties is:
[A]Low
[B]Manageable as we have done similar work before
[C]High
[D]Very low



5. The work effort for an activity is:
[A]The work units needed to complete an activity
[B]The work period available to perform the work of the project
[C]The calendar days taken to complete an activity
[D]The work units needed to complete an activity plus the weekends



6. My work time is 8 hours a day from Monday - Friday. The duration for completing activity A is 192 hours. I have 4 persons who are available full time to complete the activity. If I begin performing A on Monday what is the elapsed time for A to finish?
[A]6 workdays
[B]9 days
[C]8 days
[D]12 workdays



7. In a three time estimate using PERT, if the optimistic estimate for a task is 10 days, most likely is 15 days and pessimistic is 20 days what is the standard deviation of the task?
[A]1.67 days
[B]2 days
[C]1.37 days
[D]Insufficient information to determine the value



8. A dependency that requires that the initial design be completed before detailed design can start is an example of:
[A]Discretionary Dependency
[B]Mandatory dependency
[C]External dependency
[D]Internal dependency



9. The ______________ task relationship is the most common task scheduling relationship:
[A]Start to start
[B]Finish to start
[C]Finish to finish
[D]Start to finish



10. The preceding activity must start before the succeeding activity can finish denotes which kind of dependency?
[A]Finish to start
[B]Start to start
[C]Finish to Finish
[D]Start to finish



11. When a task cannot be completed before another task is completed, it is called a?
[A]Critical relationship
[B]Finish to finish dependency
[C]Concurrent task
[D]Finish to start dependency



12. Lag means:
[A]Amount of time a task can be delayed without delaying the project
[B]Amount of time a task can be delayed without delaying the early start date of its successor activity/activities
[C]A modification of the logical relationship in a network which delays a successor activity
[D]The amount of time a project is lagging behind from the original schedule



13. In creating your network diagram, you know that the second task cannot be started till 4 days have passed after the completion of first task due to external reasons. Another name for this compulsory wait is:
[A]Free float
[B]Float
[C]Lead
[D]Lag



14. Which term describes a modification of a logical relationship that accelerates a successor task?
[A]Lead
[B]Leveling
[C]Crashing
[D]Lag



15. A lag can occur _______:
[A]In a finish to start relationship
[B]In a finish to finish relationship
[C]In a start to start relationship
[D]All of the above



No comments:

Most Played Quizzes Last Week