GK Quiz, General Knowledge, Latest Current Affairs, Business Quiz, Management Quiz, Finance, Project Management, PMP Resources, IT Quiz, Bollywood Quiz, Finance, HR, OB, Supply Chain Management, Multiple Choice Questions, Bank PO Entrance Exam Questions, Civil Services Question Bank, Quant, Verbal, GMAT, SAT, TOEFL Resources Questions, Numerical Ability, Fun Quiz, KBC

Project Management Quiz - 69 (Project Manager)

1. A project network is a graphical display showing ……………………….:
[A]arrows and nodes
[B]sequence of project activities
[C]activities
[D]resources used in the project



2. The network is used by the project manager to:
[A]Identify relationship between tasks
[B]Optimize the usage of resources
[C]Develop the project schedule
[D]All of the above



3. To optimize and reduce the project schedule what steps should be taken?
[A]The number of activities should be reduced
[B]The duration of activities should be reduced
[C]Activities should be overlapped wherever possible
[D]Reduce the project goals



4. An activity is a fundamental……………… for managing a project:
[A]Entity
[B]Resource
[C]Work package
[D]Controlling event



5. An activity performs work given in the:
[A]Gantt Chart
[B]work package
[C]ADM
[D]PDM



6. Which one of the following is not consumed by an activity?
[A]Material
[B]Brand equity
[C]Capital
[D]Human



7. What is not characteristic of an activity?
[A]It consumes resources
[B]It is the same as a task
[C]It denotes a milestone in a network
[D]It is a basic entity on which a network is built



8. Dummy activities are used in which kind of diagramming method:
[A]ADM
[B]PDM
[C]CDM
[D]Activity on node



9. In an ADM dummy activities are used to:
[A]Show multiple critical paths
[B]Identify alternate cost flows
[C]Identify dependency relationships
[D]Link subprojects to primary project starts



10. In an ADM arrows reflect:
[A]Only direction of relationship between 2 activities from left to right
[B]Only direction of relationships between 2 activities from right to left
[C]Only an activity
[D]Both an activity and the direction between two activities



11. An activity-on-arrow diagram is same as:
[A]PDM
[B]ADM
[C]CDM
[D]PERT



12. An activity-on-node diagram is also known as:
[A]GERT
[B]PDM
[C]Gantt chart
[D]PERT



13. --------------- types of relationships are possible in PDM scheduling:
[A]Three
[B]Five
[C]Four
[D]One



14. The precedence diagramming method provides project managers with knowledge of:
[A]Tasks likely to be involved in the project integration and resource allocation functions
[B]A graphical interpretation of task inter-dependencies
[C]The project's completion date
[D]Project duration analysis showing which sequence of activities have least flexibility



15. An arrow in precedence diagramming method reflects:
[A]Only the logical relationship between 2 activities
[B]Only the activity
[C]Both an activity and the direction between 2 activities
[D]Only the direction of relationship between 2 activities from right to left



No comments:

Most Played Quizzes Last Week