GK Quiz, General Knowledge, Latest Current Affairs, Business Quiz, Management Quiz, Finance, Project Management, PMP Resources, IT Quiz, Bollywood Quiz, Finance, HR, OB, Supply Chain Management, Multiple Choice Questions, Bank PO Entrance Exam Questions, Civil Services Question Bank, Quant, Verbal, GMAT, SAT, TOEFL Resources Questions, Numerical Ability, Fun Quiz, KBC

Project Management Quiz - 58

1. The priority of the Quality function is ________ priority:
[A]Equal to cost and schedule
[B]Higher than cost and schedule
[C]Lower than cost and schedule
[D]None of the above



2. A Pareto diagram helps the project manager to :
[A]Focus on the most critical issues to improve quality
[B]Focus on stimulating thinking
[C]Explore a desired future outcome
[D]Determine if a process is out of control



3. What will be shown in a Gantt chart but not in a responsibility matrix?
[A]Time
[B]Tasks
[C]Interrelationships
[D]Who is in charge of each task



4. A work package is:
[A]The lowest level of a work breakdown structure
[B]The level of the WBS where cost data are collected
[C]Made up of multiple costs accounts
[D]A and B



5. The scope baseline is the original:
[A]Project schedule and budget
[B]Description in the project charter
[C]Project Plan plus or minus approved changes
[D]Performance measure



6. In the context of projects, temporary means that:
[A]Projects have a finite time duration with definite start and end dates
[B]Every project has a definite beginning
[C]The project can be cancelled at any point of time depending upon the whims of the senior executive
[D]Projects have no significance to the permanent sustainability of a corporation



7. A work breakdown structure is most useful for:
[A]Identifying individual tasks for a project
[B]Scheduling the start of tasks
[C]Developing a cost estimate
[D]A and C



8. If a risk has a 50% chance of happening in any given month, and if the project is expected to last for 8 months, the probability that this risk event will occur during the last month of the project is:
[A]25%
[B]50%
[C]75%
[D]100%



9. In the arrow diagramming method (ADM), __________ do not consume time or resources:
[A]Events
[B]Activities
[C]Float
[D]Arrows



10. In a three time estimate using PERT, if the optimistic estimate for a task is 6 days and pessimistic estimate is 12 days, what is the most likely estimate if the mean is 7 days:
[A]7 days
[B]8 days
[C]6 days
[D]12 days



11. A negative float is present when?
[A]The late start date is earlier than the early start date
[B]The critical path supports the imposed end date
[C]The early finish date is equal to the late finish date
[D]The late start date is later than early start date



12. Task B cannot begin until 10 days after task A begins is best described as a:
[A]Finish to start relationship
[B]Start to start relationship
[C]Start to start with a 10 days lag
[D]Start to start with a 5 day lead



13. Amongst all of the following, the most important component of project control is the:
[A]Project charter
[B]Project schedule
[C]Work breakdown structure
[D]Assignment of responsibility for work



14. Which of the following is most frequently used to indicate task relationships?
[A]Bar chart
[B]Network diagram
[C]Gantt chart
[D]Work breakdown structure



15. Preliminary cost estimates are meaningful during the _______ phase of the project:
[A]Conceptual
[B]Planning
[C]Control
[D]Execution



No comments:

Most Played Quizzes Last Week