1. The priority of the Quality function is ________ priority:
[A]Equal to cost and schedule
[B]Higher than cost and schedule
[C]Lower than cost and schedule
[D]None of the above
2. A Pareto diagram helps the project manager to :
[A]Focus on the most critical issues to improve quality
[B]Focus on stimulating thinking
[C]Explore a desired future outcome
[D]Determine if a process is out of control
3. What will be shown in a Gantt chart but not in a responsibility matrix?
[A]Time
[B]Tasks
[C]Interrelationships
[D]Who is in charge of each task
4. A work package is:
[A]The lowest level of a work breakdown structure
[B]The level of the WBS where cost data are collected
[C]Made up of multiple costs accounts
[D]A and B
5. The scope baseline is the original:
[A]Project schedule and budget
[B]Description in the project charter
[C]Project Plan plus or minus approved changes
[D]Performance measure
6. In the context of projects, temporary means that:
[A]Projects have a finite time duration with definite start and end dates
[B]Every project has a definite beginning
[C]The project can be cancelled at any point of time depending upon the whims of the senior executive
[D]Projects have no significance to the permanent sustainability of a corporation
7. A work breakdown structure is most useful for:
[A]Identifying individual tasks for a project
[B]Scheduling the start of tasks
[C]Developing a cost estimate
[D]A and C
8. If a risk has a 50% chance of happening in any given month, and if the project is expected to last for 8 months, the probability that this risk event will occur during the last month of the project is:
[A]25%
[B]50%
[C]75%
[D]100%
9. In the arrow diagramming method (ADM), __________ do not consume time or resources:
[A]Events
[B]Activities
[C]Float
[D]Arrows
10. In a three time estimate using PERT, if the optimistic estimate for a task is 6 days and pessimistic estimate is 12 days, what is the most likely estimate if the mean is 7 days:
[A]7 days
[B]8 days
[C]6 days
[D]12 days
11. A negative float is present when?
[A]The late start date is earlier than the early start date
[B]The critical path supports the imposed end date
[C]The early finish date is equal to the late finish date
[D]The late start date is later than early start date
12. Task B cannot begin until 10 days after task A begins is best described as a:
[A]Finish to start relationship
[B]Start to start relationship
[C]Start to start with a 10 days lag
[D]Start to start with a 5 day lead
13. Amongst all of the following, the most important component of project control is the:
[A]Project charter
[B]Project schedule
[C]Work breakdown structure
[D]Assignment of responsibility for work
14. Which of the following is most frequently used to indicate task relationships?
[A]Bar chart
[B]Network diagram
[C]Gantt chart
[D]Work breakdown structure
15. Preliminary cost estimates are meaningful during the _______ phase of the project:
[A]Conceptual
[B]Planning
[C]Control
[D]Execution
Project Management Quiz - 58
Tags
# PGCPM
# PMP
# PMP Certification
# PMP Questions
# Project Management
Share This
Project Management
Labels:
PGCPM,
PMP,
PMP Certification,
PMP Questions,
Project Management
Subscribe to:
Post Comments (Atom)
Most Played Quizzes Last Week
-
1. Which of the following is NOT a component of nature? Plants Animals Plastic Rocks 2. What do we call plants that grow naturally in ...
-
1. Which of the following is considered to be poor e-mail etiquette? [A]Have a proper sign off: Regards, Sincerely, etc. [B]Responding to me...
-
1. Ratan Tata was the Chairman of which of the following conglomerates? Reliance Industries Aditya Birla Group Infosys Tata Group 2. ...
-
1. What were the eight ministers called in Shivaji's regime, who assisted him in the administrative helm of affairs? Astami Ettu Astap...
-
1. We keep in touch with everyone through- means of communication means of transport means of production none 2. Which of the following are ...
-
1. When is the Prayagraj Mahakumbh 2025 scheduled to take place? January 1 - February 15, 2025 January 13 - February 26, 2025 February 1 -...
-
1. Ramakrishna Paramhansa was born on ? [A]18 January 1838 [B]18 February 1836 [C]18 February 18366 [D]18 April 1839 2. Which among the f...
-
1. What is the original name of Bangalore in Kannada language? [A]Begur [B]Bangaru [C]Bengaluru [D]None of the above 2. Once called a pens...
-
This time the quiz is focused on Banking Industry. Check out how familiar you are with these banks' logos. 1. Guess the logo? Hint:Estab...
-
1. What percentage of the Earth's surface is covered by water? 50% 60% 70% 75% 2. Which term refers to a large body of land? Island...
No comments:
Post a Comment