GK Quiz, General Knowledge, Latest Current Affairs, Business Quiz, Management Quiz, Finance, Project Management, PMP Resources, IT Quiz, Bollywood Quiz, Finance, HR, OB, Supply Chain Management, Multiple Choice Questions, Bank PO Entrance Exam Questions, Civil Services Question Bank, Quant, Verbal, GMAT, SAT, TOEFL Resources Questions, Numerical Ability, Fun Quiz, KBC

Project Management Quiz - 54

1. The Project Management Plan:
[A]Should be avoided for small projects as takes too much time
[B]Provides communication regarding the project to all the stakeholders
[C]Is like a Statement of Work
[D]None of the above



2. In today's context of change, is it worthwhile to spend more time to define the scope in clear terms?
[A]No
[B]Yes
[C]Cannot say
[D]It depends on the size of the project



3. Using the work breakdown structure indicated below, an instance of a work package is:
1.0.0. Build house
1.1.0. Excavate
1.1.1. Survey
1.1.2. Dig hole
1.2.0. Prepare foundation
[A]Build house
[B]Excavate
[C]Survey
[D]Prepare foundation



4. Work not included in the WBS is:
[A]To be detailed out later
[B]Outside the scope of the project
[C]Will be taken care of at the time of executing the project
[D]Needs management attention



5. Two techniques used for drawing project networks are known as:
[A]Activity and Arrow drawing methods
[B]Arrow and circle drawing methods
[C]ADMs and PDMs
[D]ADMs and ADCs



6. The person drawing the network must to be clear about:
[A]The project's goals and objectives
[B]The duration of each activity
[C]The logical sequence of activities
[D]All of the above



7. An activity should have a definable?
[A]Start time
[B]Finish time
[C]Cost
[D]All of the above



8. Arrow diagramming method is similar to precedence diagramming method in that:
[A]Events are connected by activities
[B]Activities are connected by dummies
[C]They are project network drawing techniques
[D]Both display the same network diagram



9. An Activity-on-node diagram is different from an activity-on-arrow diagram in that it:
[A]Is drawn with dark lines
[B]Can show four types of relationships
[C]Has only finish to start relationships
[D]Uses dummy activities



10. Program Evaluation Review Technique was developed:
[A]For US Navy
[B]For expansion project of Corning Glass
[C]By Dr. Allen Pert
[D]For developing bar charts



11. What is not a duration estimating tool/technique?
[A]Analogous
[B]Contingency planning
[C]Time variance scheduling
[D]Expert judgment



12. I cannot test the software until I code the software. This expression describes which of the following dependencies?
[A]Discretionary
[B]Soft
[C]Mandatory or hard
[D]Regulated



13. Which term describes a modification of a logical relationship that delays a successor task?
[A]Lag
[B]Lead
[C]Float
[D]Slack



14. The difference between early finish and early start is equivalent to:
[A]Duration of the next activity
[B]Duration of an activity
[C]The float to complete an activity
[D]Duration of the previous activity



15. The late start of an activity represents :
[A]The last date on which the activity must start else there would be project delay
[B]The computation based on the latest finish date minus duration
[C]The early start plus float of an activity
[D]All of the above



No comments:

Most Played Quizzes Last Week