GK Quiz, General Knowledge, Latest Current Affairs, Business Quiz, Management Quiz, Finance, Project Management, PMP Resources, IT Quiz, Bollywood Quiz, Finance, HR, OB, Supply Chain Management, Multiple Choice Questions, Bank PO Entrance Exam Questions, Civil Services Question Bank, Quant, Verbal, GMAT, SAT, TOEFL Resources Questions, Numerical Ability, Fun Quiz, KBC

Project Management Quiz - 38

1. How much time does the typical project manager spend communicating (formal and informal)?
[A]40% - 60%
[B]30% - 70%
[C]60% - 80%
[D]75% - 90%
[E]25% - 55 %



2. In which type of organization is team building likely to be most difficult?
[A]Functional
[B]Projectized
[C]Matrixed
[D]Project expediter
[E]Project coordinator



3. Problems can occur in properly defining a project because:
[A]Project goals may not be agreeable to all parties
[B]The plan was "too loose," thus allowing priorities to change
[C]Low turnover of project personnel
[D]Too much communication between the client and project personnel
[E]The project objectives were quantified



4. The cost of a quality program should be budgeted at _____ of the total project.
[A]10-12%
[B]2-3 %
[C]6-8%
[D]3-5%
[E]more than 15 %



5. The review for the specification completeness is performed during which of the following cycles.
[A]Award cycles
[B]requirements cycle
[C]requisition cycle
[D]solicitation cycle
[E]contractual cycle



6. The schedule risk is the _____ .
[A]the accumulated "expected' durations which maintain project completion.
[B]Critical Path adjusted by "high-risk" activity float.
[C]highest risk path that maintains quality.
[D]Critical Path when calculated with "most likely" duration.
[E]highest risk path that contributes the most risk toward the project completion.



7. Screening of risk events for potential risk is known as _____ .
[A]problem structuring.
[B]risk identification
[C]risk quantification
[D]risk modeling
[E]risk mitigation



8. The Cost Performance Index is computed as:
[A]budget cost of work performed divided by actual cost of work performed
[B]budget cost of work performed minus actual cost of work performed
[C]budget cost of work performed minus budget cost of work scheduled
[D]budget cost of work scheduled divided by budget cost of work performed
[E]actual cost of work scheduled divided by budget cost of work performed



9. Typical characteristics of a work package include:
[A]Representation of units of work at a level where work is performed
[B]Clearly distinguishes one work package from all others assigned to a single functional group
[C]Limits the work to be performed to relatively short periods of time
[D]All of the above
[E]A and B only



10. Which of the following is not a cost of non-conformance?
[A]maintenance and calibration
[B]warranty repairs
[C]scrap
[D]rework
[E]All of the above.



11. Which of the following is not a method of government procurement.
[A]Assistance
[B]sealed bidding
[C]competitive proposals
[D]acquisition
[E]small purchases



12. Which of the following would most likely not be an essential objective of a project team kick-off meeting
[A]Create a project technology master plan
[B]Get team members to know one another
[C]Identify project problem areas
[D]Obtain individual and group commitments
[E]Identify the project coordinator



13. You are in a meeting with someone who just ate a slice of garlic bread. Your are distracted by his pungent breath. Which of the following communication barriers describe these distractions?
[A]Sign Detection
[B]Sensory Limitations
[C]Selective Perception
[D]Varying Alertness of Perception
[E]None of the above



14. Arbitration is a _____ approach to conflict management in resolving conflict disputes.
[A]lose-lose
[B]win-win
[C]win-lose
[D]lose-win
[E]closed door



15. As project manager, you wish to impose a standard method by which subordinates calculate project costs. Which level of communication should be required for this effort?
[A]Face-to-face
[B]Telephone
[C]Written
[D]Non-verbal
[E]All of the above should be required.



No comments:

Most Played Quizzes Last Week