1. Of the following, who has the ultimate responsibility for meeting project quality objectives?
[A]Project Engineer
[B]Project Manager
[C]Functional Manager
[D]Quality Assurance Manager
[E]Project Owner
2. Risk mitigation involves all but which of the following:
[A]developing system standards (policies, procedure, responsibility standards)
[B]obtaining insurance against loss
[C]identification of project risks
[D]performing contingent planning
[E]developing planning alternatives
3. The cost of corrective action taken by the purchaser and chargeable to the supplier under the terms of the contract is:
[A]Payment authorization
[B]Bid cost considerations
[C]Release payment
[D]Back charge
[E]None of the above.
4. The sequential steps that define the process for successfully completing a project is:
[A]Implementation Plan
[B]a life cycle
[C]Development Plan
[D]a critical path
[E]Management Plan
5. Which of the following time robbers end up creating additional work for the project manager and the project office?
[A]Failure to delegate
[B]Changes without notification or direction
[C]Unreasonable time constraints
[D]Over directing people
[E]All of the above
6. You are giving your team instructions on how to perform a new test which is different from the way that the team had performed it previously. The best way to verify that the learn understands what you want is to:
[A]obtain feedback
[B]analyze the team's perceptions barriers
[C]uses gestures in presenting the instructions
[D]analyze the team's decoding skills
[E]analyze the team's encoding skills
7. A common way by which executives provide the project manager with written authority is through:
[A]A common job description for all project managers
[B]An appointment letter
[C]A project charter
[D]All of the above
[E]B and C only
8. Surveys have shown that the primary skill needed to be a project manager is communication skill. The typical project manager spends approximately ______percent of his or her time communicating.
[A]40-50
[B]50-60
[C]60-75
[D]75-90
[E]90-95
9. The Work Breakdown Structure (WBS) is the basis for communicating:
[A]Project scope, cost control, schedule, quality
[B]Project objectives, dependencies, plan, cost control
[C]Project scope, schedule, staffing, cost control
[D]Project scope, quality, schedule, dependencies
[E]Project budget, schedule, risk factors, work assignments.
10. The quality objectives are approved in the conceptual stage of the project by the:
[A]Project Engineer
[B]Project Manager
[C]Functional Manager
[D]Quality Assurance Manager
[E]Project Owner
11. Total Project Risk:
[A]should not be calculated for small projects
[B]is the probability of each project risk event times the sum of the consequences of individual project risk events which could occur during the project.
[C]Is the cumulative sum of the probability of each individual project risk event times the consequences of occurrence of that risk event.
[D]A and B
[E]A and C
12. _____ is a narrative description of the work to be accomplished or resource to be supplied.
[A]Purchase order
[B]Level of effort work
[C]Scope of work
[D]Contract stipulation
[E]None of the above.
13. A line manager provides you with three estimates for his activity in your PERT network. His estimates are 2 weeks optimistically, 4 weeks most likely, and 12 weeks pessimistically. The expected time which would appear on the chart would be:
[A]4 weeks
[B]5 weeks
[C]6 weeks
[D]7 weeks
[E]None of the above.
14. In Project Risk Management, Risk Response may include actions to:
[A]reduce the probability of risk events
[B]change the scope, budget, schedule or quality specifications of the project
[C]reduce the consequences or severity of impacts of a potential risk event
[D]A and C
[E]All of the above.
15. Researching, organizing and recording pertinent information is called:
[A]Alternative analysis
[B]Information gathering
[C]Configuration management
[D]Post project analysis
[E]All of the above
Project Management Quiz - 25
Tags
# PGCPM
# PMP
# Project Management
Share This
Project Management
Labels:
PGCPM,
PMP,
Project Management
Subscribe to:
Post Comments (Atom)
Most Played Quizzes Last Week
-
1. Where was Guru Gobind Singh Ji born? [A]Patna [B]Anandpur [C]Amritsar [D]Bhopal 2. Guru Gobind Singh Ji was the _____ sikh guru? [A...
-
1. Where did Atal Bihari Vajpayee born? [A]Gwalior [B]Lucknow [C]Balia [D]Kanpur 2. When did Atal Bihari Vajpayee born? [A]25 December 19...
-
1. Which of the following is considered to be poor e-mail etiquette? [A]Have a proper sign off: Regards, Sincerely, etc. [B]Responding to me...
-
1. There are two universities which are named in honour of Ahilya Bai. One is Devi Ahilya Vishwa Vidyalaya in Indore, Madhya Pradesh and the...
-
1. What was the old name of Varanasi(Banaras)? [A]Patliputra [B]Magadh [C]Indraprastha [D]Kashi 2. On which river bank Varanasi is situated...
-
1. Ratan Tata was the Chairman of which of the following conglomerates? Reliance Industries Aditya Birla Group Infosys Tata Group 2. ...
-
1. Which city is called the Pink city? Lucknow Hyderabad Jaipur Kanpur 2. Which city is called the city of Lakes? Delhi Bengaluru Mumbai Uda...
-
1. When was Sri Aurobindo born? [A]15th August 1872 [B]12th May 1872 [C]1st April 1872 [D]16th July 1872 2. Who was Sri Aurobindo...
-
Mental Ability and Logical Reasoning MCQs and Aptitude Quizzes Mental reasoning and general mental ability is one of the main topics o...
-
The Logo Quiz is dedicated to all the Logo and Quizzing enthusiasts across the world. This week's theme is Oil and Gas, Energy Sector. A...
No comments:
Post a Comment