GK Quiz, General Knowledge, Latest Current Affairs, Business Quiz, Management Quiz, Finance, Project Management, PMP Resources, IT Quiz, Bollywood Quiz, Finance, HR, OB, Supply Chain Management, Multiple Choice Questions, Bank PO Entrance Exam Questions, Civil Services Question Bank, Quant, Verbal, GMAT, SAT, TOEFL Resources Questions, Numerical Ability, Fun Quiz, KBC

Project Management Quiz - 24

1. Formal authority is often referred to as legitimate power. Which two other forms of power are also considered to be legitimate power?
[A]Reward and penalty
[B]Reward and referent
[C]Referent and expert
[D]Expert and reward
[E]Penalty and referent



2. Power games, withholding information, and hidden agendas are examples of-.
[A]noise
[B]communication barriers
[C]indirect communication
[D]mixed messages
[E]All of the above



3. Scope management is:
[A]a project control function.
[B]employs change control.
[C]a work authorization process.
[D]considers Cost, Quality and Schedule.
[E]All of the above.



4. The most common method for pricing out non-burdened labor hours for a three year project would be to:
[A]Price out the hours at the actual salary of the people to be assigned.
[B]Price out the work using a company-wide average labor rate.
[C]Price out the work using a functional group average labor rate.
[D]All of the above.
[E]A and B only.



5. The principles of risk management should be followed only for:
[A]complex projects
[B]simple projects
[C]large projects
[D]A and C
[E]All of the above.



6. Utility Theory:
[A]considers the risk propensity of the decision makers.
[B]is based on proven statistical methods.
[C]deals with the usefulness of the end product.
[D]is a key element of ISO 9000
[E]B and C



7. Which is not part of the purchasing cycle?
[A]Defined need
[B]Transmit need
[C]Inspection
[D]Prepare and issue purchase order
[E]A and D



8. A network has been developed with resources from six different departments. One of the six departments has just informed you that they can increase the number of employees from 5 to 8. This will result in:
[A]A shortening of the critical path.
[B]A shortening of the noncritical path.
[C]A decrease in the total cost of the project.
[D]An increase in the cost of the project.
[E]A through D are possible based upon where the resources are deployed.



9. Conflict management requires problem-solving. Which of the following is often referred to as a problem-solving technique and used extensively in conflict resolution?
[A]Confrontation
[B]Compromise
[C]Smoothing
[D]Forcing
[E]Withdrawal



10. Cost Reimbursable contracts are equivalent to:
[A]Cost plus contracts
[B]Fixed plus contracts
[C]Progress payment contracts
[D]Back charge contracts
[E]None of the above.



11. In project-driven companies, costs are usually billed againest the project based upon:
[A]The burdened labor rate of the actual employees who performed the work.
[B]The burdened labor rate of the line organization average salary.
[C]The burdened labor rate of the company average salary.
[D]The burdened labor rate of the average salary of the project team members.
[E]None of the above.



12. Project Risk Management is based on which of the following premises:
[A]the future is unknown.
[B]unknowns can result in risks or opportunities.
[C]we cannot control risk events.
[D]project risk impact can be measured and controlled
[E]All of the above.



13. The project manager that allows and supports group discussions and decision making is called a(n) _____ manager.
[A]autocratic
[B]consultant autocratic
[C]consensus
[D]shareholder
[E]None of the above.



14. What is the purpose of the Project Plan?
[A]To document the Preliminary estimates.
[B]To document the Definitive estimates.
[C]To document the Budgetary estimates.
[D]To document Parametric estimates.
[E]To document Order of Magnitude estimates.



15. Management has decided to "crash" a project in order to avoid penalty payments for late deliveries. To crash the project, either overtime or additional resources should be assigned to:
[A]All activities.
[B]Only those activities with the longest time durations.
[C]Those activities on the critical path begining with the longest time duration activities.
[D]Those activities with the greatest degree of risk.
[E]None of the above.



No comments:

Most Played Quizzes Last Week