GK Quiz, General Knowledge, Latest Current Affairs, Business Quiz, Management Quiz, Finance, Project Management, PMP Resources, IT Quiz, Bollywood Quiz, Finance, HR, OB, Supply Chain Management, Multiple Choice Questions, Bank PO Entrance Exam Questions, Civil Services Question Bank, Quant, Verbal, GMAT, SAT, TOEFL Resources Questions, Numerical Ability, Fun Quiz, KBC

Project Management Quiz - 15

1. Which of the following utility functions reflects risk-aversion:
[A]uniform
[B]increasing
[C]decreasing
[D]exponential
[E]B and D only



2. A deficiency in characteristics that render the quality of the material/service unacceptable is usually referred to as:
[A]defective
[B]defect
[C]non-conformance
[D]poor workmanship
[E]lack of fitness for use



3. A line manager possesses information which the project team needs, but withholds the information. The results in a(n):
[A]Blindspot
[B]Facade
[C]region of influence
[D]Communication power base
[E]None of the above



4. A project can best be defined as:
[A]Series of non-related activities designed to accomplish single and multiple objectives.
[B]Coordinated effort of related activities designed to accomplish a goal without a well-established end point.
[C]Cradle-to-grave activities which must be accomplished in less than one year and consumes human and non-human resources.
[D]Any undertaking with a definable time frame, well-defined objectives, and consumes both human and non-human resources with certain constraints.
[E]All of the above.



5. Guidelines for estimating time durations include:
[A]Assuming a normal level of labor and equipment.
[B]Assuming a normal work week.
[C]Using consistent time units
[D]Using past actual durations as guides.
[E]All or part of each of the above.



6. Herzberg identified factors which, if present, will lead to increased motivation. A typical factor would be:
[A]Good supervision
[B]Job security
[C]Regular promotions
[D]Good salary
[E]A dental plan



7. Statistical cost estimating techniques (based upon history), are called _____ estimates and are a _____ approach.
[A]Definitive, bottom up.
[B]Analogy, top down.
[C]Parametric, bottom up.
[D]Parametric, top down.
[E]Analogy, bottom up.



8. Which quality management tool would be used to determine potential causes of a production problem?
[A]control chart.
[B]Ishikawa diagram.
[C]scatter diagram.
[D]histogram.
[E]run chart.



9. Affinity diagrams are used to:
[A]determine if a process is in control.
[B]determine root cause.
[C]show the relationship among variables.
[D]categorize large amounts of data.
[E]None of the above.



10. One of your project team members has made a technological breakthrough on an R & D project. The result will be new business for the company, as well as a company patent. The team member received a company bonus. The motivational strategy used here is:
[A]Job enrichment
[B]Linking pay and performance
[C]Behavior modification
[D]Freedom in the work place
[E]All of the above



11. Smoothing out resource requirements from period to period is called resource _____.
[A]Allocation.
[B]Partitioning
[C]Leveling.
[D]Quantification
[E]None of above.



12. The most precise or accurate estimate for determining project costs is the _____ estimate.
[A]Definitive.
[B]Analogy
[C]Budget
[D]Modified standards.
[E]Rule of thumb.



13. When subordinates know pertinent information that is not known by the project manager, the result is:
[A]Blindspot
[B]Facade
[C]region of influence
[D]Communication power base
[E]None of the above



14. Which of the following scheduling methods uses more of the risk management concepts:
[A]ADM
[B]PDM
[C]CPM
[D]PERT
[E]Gantt



15. Which of the following terms refers to the situation where the work is being used for the purpose intended and so certified:
[A]beneficial completion
[B]substantial completion
[C]project completion
[D]contract closeout
[E]final completion