1. When working in an environment that uses learning curves, the most effective plan for creating the perception that pay is related to performance is to provide the team members with an individual salary plus bonus based upon
[A]Individual productivity
[B]Cost effectiveness
[C]Group or team productivity
[D]Rating system developed by the project manager
[E]All of the above
2. Which of the following is not part of the acquisition process:
[A]source selection
[B]invitation to bid
[C]contract award
[D]notice to proceed
[E]All of the above are parts of the acquisition process.
3. An individual who is working on the satisfaction of physiological needs has essentially satisfied which needs?
[A]Safety
[B]Empowerment/authority
[C]Esteem
[D]Self-actualization
[E]None of the above
4. In the PDM, common constraints include:
[A]Start-to-start
[B]Finish-to-start
[C]Finish-to-finish
[D]B and C only
[E]A, B, and C.
5. Scope reporting is the timely determination, _____, and _____ of project progress, status data, and transforming this into structured documentation (reports) necessary to judge project performance (reporting on work packages).
[A]Recording, accumulation.
[B]Recording, graphical display.
[C]Accumulation, graphical display.
[D]Graphical display, interpretation.
[E]Interpretation, analysis.
6. There are two major types of reserves used on projects. The _____ is for (usually major) scope changes that were not considered as part of the original plan, whereas the _____ is to compensate for minor changes in estimating, escalation factors.
[A]Management reserve, unplanned allowance fund.
[B]Management reserve, contingency.
[C]Contingency fund, management reserve.
[D]Unplanned allowance fund, budgetary reserve.
[E]Unplanned reserve, planned reserve.
7. To determine what causes the majority of quality problems in a process, a very useful tool is the:
[A]cause and effect diagrams.
[B]flow chart.
[C]control chart.
[D]pareto chart.
[E]trend chart.
8. Which of the following is not part of contract administration
[A]contract award
[B]performance control
[C]financial control
[D]contract closeout
[E]All of the above are parts of contract administration.
9. A(n) _____ system is designed to ensure the timely availability of nonhuman resources, and includes the cost in procurement, shipping/freight, storage and loss.
[A]Inventory control.
[B]Materials management.
[C]Procurement.
[D]All of the above.
[E]A and C only.
10. Expectancy theory as applied to project management implies that:
[A]The team will work the hardest on those goals that are clearly explained by the project manager
[B]The more rewards that the project manager provides, the better the performance of the team
[C]Team members will work hardest for those project goals that also bring satisfaction to personal goals
[D]Employees will work hardest for those project goals which are accompanied by high levels of authority for the individual team members
[E]None of the above
11. Non-verbal communication includes:
[A]Body movement
[B]Gestures
[C]Facial expressions
[D]The way we move our hands
[E]All of the above
12. The formal invitation to submit a price for specified goods/services is usually referred to as:
[A]request for proposal
[B]request for quotation
[C]tender invitation
[D]bid invitation
[E]A and B only
13. The project scope/charter baseline includes:
[A]Summary of background conditions defining the project.
[B]Organization, authority and responsibility relationships.
[C]Functions to be performed.
[D]Resource requirement schedule including time estimates.
[E]All of the above.
14. Which of the following is not an input to quality planning?
[A]scope statement.
[B]regulations.
[C]work results.
[D]standards.
[E]quality policy.
15. Which of the following networking methods allows us to show that the last 10% of one element cannot be completed until 62% of a previous element has been completed?
[A]PERT
[B]ADM
[C]PDM
[D]All of the above.
[E]A and C only.
Project Management Quiz - 14
Tags
# PGCPM
# PMP
# Project Management
Share This
Project Management
Labels:
PGCPM,
PMP,
Project Management
Subscribe to:
Post Comments (Atom)
Most Played Quizzes Last Week
-
1. Where was Guru Gobind Singh Ji born? [A]Patna [B]Anandpur [C]Amritsar [D]Bhopal 2. Guru Gobind Singh Ji was the _____ sikh guru? [A...
-
1. Where did Atal Bihari Vajpayee born? [A]Gwalior [B]Lucknow [C]Balia [D]Kanpur 2. When did Atal Bihari Vajpayee born? [A]25 December 19...
-
1. Which of the following is considered to be poor e-mail etiquette? [A]Have a proper sign off: Regards, Sincerely, etc. [B]Responding to me...
-
1. There are two universities which are named in honour of Ahilya Bai. One is Devi Ahilya Vishwa Vidyalaya in Indore, Madhya Pradesh and the...
-
1. What was the old name of Varanasi(Banaras)? [A]Patliputra [B]Magadh [C]Indraprastha [D]Kashi 2. On which river bank Varanasi is situated...
-
1. Ratan Tata was the Chairman of which of the following conglomerates? Reliance Industries Aditya Birla Group Infosys Tata Group 2. ...
-
1. Which city is called the Pink city? Lucknow Hyderabad Jaipur Kanpur 2. Which city is called the city of Lakes? Delhi Bengaluru Mumbai Uda...
-
1. When was Sri Aurobindo born? [A]15th August 1872 [B]12th May 1872 [C]1st April 1872 [D]16th July 1872 2. Who was Sri Aurobindo...
-
Mental Ability and Logical Reasoning MCQs and Aptitude Quizzes Mental reasoning and general mental ability is one of the main topics o...
-
The Logo Quiz is dedicated to all the Logo and Quizzing enthusiasts across the world. This week's theme is Oil and Gas, Energy Sector. A...
No comments:
Post a Comment